Description

FairWind took on the Installation of 22 Siemens Gamesa SG
6.6-170 T165 turbines for SGRE, each with eight
tower sections.

  • Pre-assembly to final installation
    was completed within a timeframe of
    six months
  • Two shift operations for installation and
    one shift for internal finishing

 

Results

  • Efficient execution of the pre-assembly and installation process
  • Maintained safety and quality standards throughout the project
  • Successfully completed phase one of the installation within the scheduled timeframe.

 

Read more here or contact us for service type.